A Middle Years area is the part of a public library set aside for kids in grades 4 to 7. In 2026 the City of North Vancouver added one to North Vancouver City Library, inside the main-floor children’s area: a large open room with high ceilings and a mostly glazed perimeter. Enduro built it as general contractor.
What the City asked for.
The City put the work out through an Invitation to Tender. Enduro won it and signed a fixed-price CCDC 2 contract, building to the drawings and specifications of the prime consultant, Space Design Inc.
The design splits the area into two zones. The active zone is for group work, gathering and the public computers. The quiet zone has soft seating for kids who want to read, study or work in pairs. Moving some shelving and collections to another part of the department was also meant to cut the noise that carries from the children’s area up to the library’s upper floors.
Ceilings that take the noise
The tender called for ceiling features with acoustic treatment in a room with high ceilings and a mostly glass perimeter. Felt ceiling clouds in green, yellow and white now hang over both zones, alongside a new lighting package. New carpet tile and rubber base went down across the area.
Shelving taken apart and put back
The library’s existing cantilever shelving was dismantled and reinstalled in a new layout, with more shelving added to match it. The layout was sealed by an engineer, and the floor was scanned at every new shelving location before anything was fixed to it.
Millwork display panels, pony walls and shelving end panels went in, along with a feature wall and a wood slat wall. Power poles and floor raceway bring power to the active zone’s tables and computers.
Working in a library that had to stay open.
The City’s tender said the building would stay occupied and its operations were not to be affected by construction. The library would keep its regular hours, 9 a.m. to 5 p.m. or 9 p.m. depending on the day, the whole time the work was on.
Temporary dust-proof hoarding closed the work area off from the rest of the library before selective demolition began. The City needed advance notice of any loud work, and working hours had to follow its noise bylaw. Because the building was in use throughout, the tender also asked for a schedule and sequence that took the least possible time.
Substantially complete in September 2026.
The electrical work ran under an electrical permit from the City of North Vancouver and passed its rough-in and final inspections. Space Design Inc. certified substantial performance in September 2026.
We do this kind of municipal work across Metro Vancouver: public buildings renovated while people keep using them. See more of our projects, read about our municipal work, or tell us about yours.